We have 2 date parameter WeekEnding Start Date And WeekEnding Endate
which is generally starts on
Saturday to Saturday
Saturday to Sunday Only
say 10th MAy to 11th May
The actual Work Date will begin with the earliest Work Day of start Weekending date and continue till 8 days.
i.e
05/03 , 05/04 , 05/05....... 05/11
and the amount of hours need to find for each day as well, which is store in DailyEntires table.
Attached screenshot for the same.